DK | UK

CIP-plants - references

FlowTech has been following the development in the field for 20 years. For the last 20 years we gave provided several CIP plants to process-lines producing everything from marmalade to cheese.

AS Røra Fabrikker, Inderøy Norway

Duration of the project: almost 2000 hours

Construction and implementation of a 2-string CIP plant:

  • Projection of the CIP plant
  • Construction of the CIP plant
  • Projection of flow in relation to the new CIP system
  • Assembling of supply and return-pipes
  • Assembling of pipes for orange juice

Endrup Andelsmejeri , Denmark

Projection, delivery, assembling and commissioning of:

  • CIP plant
  • Whey separator and whey Pasteur
  • Acid boilers
  • Delivery of control systems
  • Renovation of an older dairy

Synnøve Finden Meirier ASA, Alvdal Norway

  • 2 complete CIP plants
  • Projection of a cheesemaking dairy
  • Assembling, construction and commissioning of a dairy
  • Ongoing addition of the dairy

APV Norge A/S, Norway

Projection, assembling and commissioning of:

  • Washer for cheese mould
  • Complete CIP plant

CIP-anlæg

 

 

FLOWTECH A/S • Højlundvej 5 • Voervadsbro • DK-8660 Skanderborg • Tel. +45 7578 2188 • Fax: +45 7578 2443 • info@flowtech.dk